Ten-Year Road Plan
The Highway Superintendent and Town Administrator work together to keep a ten-year plan for road work. This plan tracks sources of funds (Chapter 90, taxpayers, grants) and uses of funds (typically engineering, construction, and debt service). The following is the current view of which road projects will be worked on when.
FY26
- Construction for Hobbs Road Culvert Replacement
- Mill and resurface Ball Hill Road (Brooks Station to Worcester Road)
FY27
- Wheeler Road
FY28
- Reclaim and pave Bigelow Road
FY29
- Mill and repave Mirick Road between Beaman Road and Pine
FY30
- To be determined
FY31
- To be determined
FY32
- Rhodes Road
FY33
- Mountain Road (Westminster Town Line to Pine Hill Road)
- Ralph Road
- Blood Road
FY34
- Allen Hill Road
- Radford Road
- Jillian
- StageCoach
