Private Entrance / Driveway Permit Instructions
Factors for Approval
- The width and flare of the driveway where it meets the road (since the road surface must not be disturbed and the gutter line must be maintained)
- Control of storm water runoff from the property
What You Need Before You Apply
Mark Your Driveway Location
Stake out the proposed location of the driveway on the lot.
Required Plan of Proposed Work
A sketch of your lot showing:
- All lot lines and dimensions
- Driveway layout with elevations
- Distance in feet from property line to edge of proposed driveway
- Driveway construction details including berms, culverts, etc., width and flare of driveway, and roadway construction details
Process for Applying for a Permit
- Access ePermitting
- Log in or Create account
- Complete the Private Entrance application
- Click on “Driveway Conditions Form” to download it
- Complete the form and upload it to application
- Upload your Plan of Proposed Work
Permit Review and Approval by DPW Director
- Review of the application
- Completes an initial site inspection
- Approve the application for construction
- If all information is provided and requirements are met, the Director will sign off on the Pre-inspection on the online Private Entrance Permit application
After Driveway Construction (Pre-Paving)
- Notify the DPW Director or his designee of the need for an inspection at least 72 hours prior to any paving to ensure that all conditions have been met
- If the Director is satisfied, he will sign off on the final inspection card and the Building Department may issue an occupancy permit
Note
All costs relative to the processing of the driveway permit, including any review costs, will be borne by the applicant. A re-inspection fee may apply if more than three inspections are required.